Change Order Explanation for the Customer
Turns the contractor's notes about a change in the job (a customer request, a surprise found behind a wall, or a material swap) into a clear written explanation of what changed, why, what it costs, and how it affects the schedule.
Before and after
Hi Lynn,
This is Manuel Hopkins at Glenfield Construction with Change Order #2 for your kitchen remodel at 6757 Fallowfield St. Luke Grant opened the wall behind the sink and found a few things we want to walk you through. Here is each one, what it costs, and what it does to the schedule.
Recommended now
- Replace the supply pipe behind the sink: $1,180. The old galvanized pipe is corroded and weeping at a joint, and the drywall behind it is wet. We recommend replacing that run with new pipe, done by our licensed plumbing sub. Adds 2 working days together with the subfloor repair.
- Replace the soft subfloor by the dishwasher: $920. About 12 square feet of subfloor is soft. We will cut it out and replace it. Included in the 2 added working days above.
Customer requested
- Under cabinet lighting: $740 for fixtures and installation. Adds 1 working day.
Money summary
- Original contract: $28,400
- Previously approved change (range outlet move): $650
- Contract before this change order: $29,050
- This change order: $1,180 + $920 + $740 = $2,840
- New contract total if all approved: $31,890
If you approve only some items, here are the totals:
- Pipe and subfloor only: $2,100, new contract total $31,150
- Lighting only: $740, new contract total $29,790
Schedule
Pipe and subfloor add 2 working days. The lighting adds 1 day. All three add 3 working days.
How to approve
You can sign the change order or reply to this message. You can approve all of it, some of it, or none of it. If you decline an item, we will note it as your decision.
Questions or want to talk it through? Call me at 234-555-0126.
Manuel Hopkins
Glenfield Construction
Questions for the owner
- You mentioned a pot filler but gave no price. Do you want it added to this change order, and at what cost and schedule effect?