Material Order List with Waste Allowance
Takes your measured quantities and your own waste percentages and turns them into a clean order list.
Before and after
Material Order List
Job: Ross basement finish
Customer: Margot Ross
Address: 1960 Larkridge St, Larkglen
Delivery contact: Malcolm Riley, 319-555-0182
Sign-off: Magnus Randall
-
Studs, 8 ft
Need: 27
Waste: 10%
With waste: 27 x 1.10 = 29.7
Order: 30 studs -
Plate lumber, 12 ft boards
Need: 3 runs x 34 ft = 102 ft
Waste: 10%
With waste: 102 x 1.10 = 112.2 ft
Boards: 112.2 / 12 = 9.35
Order: 10 boards (covers 120 ft) -
Drywall, 1/2 in, 4 x 8 sheets (32 sq ft each)
Need: walls 68 x 8 = 544 sq ft, plus ceiling 14 x 20 = 280 sq ft, total 824 sq ft, minus 40 sq ft for door and window = 784 sq ft
Waste: 10%
With waste: 784 x 1.10 = 862.4 sq ft
Sheets: 862.4 / 32 = 26.95
Order: 27 sheets (covers 864 sq ft) -
Fogbank Oak luxury vinyl plank
Need: 280 sq ft
Waste: 8%
With waste: 280 x 1.08 = 302.4 sq ft
Boxes: 302.4 / 23.4 = 12.92
Order: 13 boxes (covers 304.2 sq ft) -
Baseboard, 8 ft pieces
Need: 68 ft minus 3 ft door = 65 ft
Waste: 10%
With waste: 65 x 1.10 = 71.5 ft
Pieces: 71.5 / 8 = 8.94
Order: 9 pieces (covers 72 ft) -
Construction adhesive
Need: 4 tubes
Waste: 0% (as you specified)
Order: 4 tubes
Please check these quantities against the plans and the actual site measurements before the order goes in.
Questions for the owner
- Which supplier is this going to, and what delivery date do you want?
- Do you want prices added? None were given.
- Do you want fasteners, tape, joint compound, or insulation on this order? None were listed, so none were added.
- Do you want flooring transition strips or trim for the door opening on the list?
What it does
Takes your measured quantities and your own waste percentages and turns them into a clean order list. Each line shows the math and the whole number of boards, sheets, boxes, or pieces to order, rounded up so you do not come up short.
Use it when: Use when a general contractor needs a material order list with a waste allowance added, such as 'figure my material order', 'add waste to this takeoff', 'how many sheets or boxes do I order', or 'make a supplier order list for this job.'