SCOPE OF WORK
Customer: Hazel Haddad
Job address: 2549 Birchbury St, Beechbrook
Customer phone: 206-555-0175
Contractor: Brightbury Builders, 206-555-0174
Walkthrough by: Henry Khan
Planned start: June 9, about 3 weeks
Project summary
We will remodel the 5x8 hall bathroom at 2549 Birchbury St. The old tub, tile surround, vanity, toilet, and vinyl floor come out, and a new alcove tub, tiled tub walls, tiled floor, vanity, toilet, fan, and paint go in.
Work by phase
Phase 1: Protection and demolition
- Protect the hallway floor
- Remove the tub, tile surround, vanity, toilet, and vinyl flooring
- Haul all debris away
Phase 2: Rough-in work
- Install new backer board on the tub walls
- Plumbing by Herman Lowry, licensed plumber: set the new tub and shower valve
- Electrical by Holly McCoy, licensed electrician: replace the bath fan and add a GFCI outlet by the vanity
Phase 3: Tile
- Tile the tub walls with 3x6 white subway tile up to 84 inches
- Tile the floor with 12x12 gray porcelain tile
- Set with thinset and finish with grout in the color Hazel chooses
Phase 4: Fixtures and finish
- Plumbing by Herman Lowry: connect vanity supply lines, set the toilet, and install the shower valve trim in chrome
- Install the vanity and mirror
- Paint walls and ceiling in one color chosen by Hazel
Materials and fixtures
Supplied by Brightbury Builders:
- Backer board
- 3x6 white subway tile
- 12x12 gray porcelain floor tile
- Thinset and grout
- New bath fan
- Paint
- Shower valve and trim in chrome
Supplied by Hazel Haddad:
- Norrvik Soak 60 alcove tub, 60 inch, white
- Tavolo Nine vanity, 36 inch, walnut, with top
- Mirror
Not included
- Hallway painting
- Heated floor
- Moving walls or drains
Customer responsibilities
- Choose the paint color and grout color by May 23
- Have the tub delivered by May 30
- Clear the bathroom before work starts
- Give us access 7 to 5, weekdays
Recommended additions, not yet in the scope
- Subfloor replacement at the tub end. Henry found a soft spot about 2 ft by 3 ft right at the tub end. We recommend replacing that section. Hazel plans to look at it after demolition and will let us know her decision. A price will be added once we confirm it.
Price and payment
Contract price: $14,850
- $4,455 at start (30%)
- $5,940 when rough-in is done (40%)
- $4,455 at finish (30%)
Permits
Brightbury Builders pulls the permit. The permit fee is charged to Hazel at our cost. Please confirm any permit and code questions with the local building department.
Changes
Any change to this scope is agreed in writing before the work starts.
We suggest having a lawyer review the final contract.
Questions for the owner
- What is the price for the subfloor replacement, and should it be added as a line once Hazel decides?
- Do you want a warranty statement in this document? If so, what are the terms?
- What is the permit fee amount, if you know it yet? Please also confirm any permit and code questions with the local building department.
- Who is supplying the new toilet, you or Hazel? It is being set but is not in either supply list yet.
- Should the paint finish (flat, satin, and so on) be listed?
What it does
Turns your walkthrough notes and job details into a clear written scope of work that tells the customer exactly what is included, who supplies what, what is not included, and what you need from them. It works for small repairs and for full remodels.
Use it when: Use when a general contractor needs to turn walkthrough notes, measurements, and job details into a clear written scope of work for a customer, such as: write up the scope, scope of work for this job, what's included and what's not, or put this remodel in writing.